An occupancy certificate (OC) is the local authority's permission to live in a building. For a new flat in Hubballi (Hubli) or Dharwad, it is the document that turns a finished structure into a home you can legally occupy, connect to the grid, mortgage and later sell. Since a Supreme Court ruling in December 2024, it has also become the document that decides whether a building gets permanent electricity and water at all.
This guide explains what the OC and the completion certificate are, who issues them in Hubballi-Dharwad, why they matter to you as a buyer, and what Karnataka's 2025-26 relaxations changed. It is general information, not legal advice.
Completion certificate and occupancy certificate
The two are often mentioned together but certify different things. The Real Estate (Regulation and Development) Act, 2016 defines both (RERA Act text):
| Completion certificate | Occupancy certificate | |
|---|---|---|
| What it says | The project has been developed according to the sanctioned plan, layout plan and specifications (section 2(q)) | The building may be occupied, as provided under local laws, and has provision for civic infrastructure such as water, sanitation and electricity (section 2(zf)) |
| Who issues it | The competent authority that sanctioned the plan | The local authority |
| Why you need it | Proof the building matches what was approved | Proof you may move in, and the basis for utilities, loans and resale |
Within corporation limits in Hubballi-Dharwad, the authority is the Hubballi-Dharwad Municipal Corporation (HDMC), which works under the Karnataka Municipal Corporations Act, 1976. Section 310 of that Act, titled "Completion certificate and permission to occupy or use", says no one may occupy a new building until the Commissioner gives permission, or until thirty days pass after the notice of completion without the Commissioner refusing it (extract in LA Bill No. 53 of 2025). The builder, not the buyer, files the notice of completion and obtains the OC.
Why the OC matters to you
Possession. RERA makes the builder responsible for obtaining the completion certificate or OC and making it available to buyers individually or to the association (section 11(4)(b)). You, in turn, must take physical possession within two months of the OC (section 19(10)). Where no local law sets a period, the builder must register the conveyance deed in your favour within three months of the OC (section 17(1)).
Utilities and loans. In Rajendra Kumar Barjatya v. U.P. Avas Evam Vikas Parishad, decided on 17 December 2024, the Supreme Court directed that electricity, water and sewerage connections be given only after the completion or occupation certificate is produced, that banks verify the certificate before lending against a building, and that builders undertake to hand over possession only after obtaining it (The Tribune, 1 January 2025).
Tax. A flat bought after the completion certificate, with the whole price paid after that date, carries no GST; see GST on under-construction flats.
Resale and records. Transferring the khata and property tax into your name, and selling later, are far simpler with an OC on file; see khata transfer after purchase.
Karnataka's 2025-26 debate on power and water without an OC
The Supreme Court ruling exposed a large backlog. By June 2025, The Hans India reported that more than 3 lakh building owners in Karnataka were stuck without connections, and that the order applied to all new buildings (The Hans India, 28 June 2025). The state's response came in steps:
- September 2025, Bengaluru. An order exempted residential buildings on plots of up to 1,200 sq.ft (ground plus two floors, or stilt plus three) within the Greater Bengaluru Authority from needing an OC. Larger residential and commercial buildings still need one (Oneindia, 10 September 2025). The government said the exemption covers individual residential buildings, not high-rise apartments or commercial complexes (The Hans India, 15 October 2025).
- Cabinet, September 2025. The Cabinet cleared power connections for certain buildings in Bengaluru without an OC and decided on a special law for a one-time relaxation, describing it as not a blanket waiver for future violations (The Hans India, 27 September 2025).
- The law. A 2025 amendment Bill added a power in the Karnataka Municipal Corporations Act for the government to notify categories of buildings exempt from the OC (new section 310(3)), with a matching change for smaller towns (LA Bill No. 53 of 2025).
- June 2026. The Bengaluru exemption was extended to plots of up to 2,400 sq.ft and ground plus three floors (Cyril Amarchand Mangaldas via Conventus Law, July 2026). A separate order of 22 June 2026 gave a 15-day, one-time window for permanent power to residential buildings of up to ground plus three floors (about 2,400 sq.ft, with a 20% tolerance) completed by 31 May 2026, in Bengaluru and in urban local bodies. About 3 lakh applications were pending statewide, about 1 lakh of them with BESCOM (Construction World, 29 June 2026).
What this means for a flat buyer. Every relaxation so far is aimed at small, individual houses. None of them covers an apartment building, and the law firm note above stresses that an exemption does not regularise a building that breaks its plan. For a flat in Hubballi-Dharwad, assume that permanent power from HESCOM, the water connection and your bank's loan all still depend on an OC.
Worked example: what the OC is worth in money
Say you are choosing between two similar ₹75 lakh flats in Hubballi.
| Flat A: OC issued, full price paid after it | Flat B: nearly finished, no OC yet | |
|---|---|---|
| GST | Nil | 5% on instalments, ₹3,75,000 on the full price |
| Stamp duty and registration (7.6%) | ₹5,70,000 | ₹5,70,000 |
| Permanent electricity and water | Available now | Only after the OC |
| Home loan | Bank can verify the OC at once | Bank must check the project's status |
Flat B may still be a sound purchase from a builder with a good record, but you carry the risk and the extra tax until the OC arrives. Stamp duty figures are from our stamp duty guide; duty is on the higher of the price and the guidance value.
How to check an OC before you pay
- Ask for a copy of the OC and the completion certificate, and the sanctioned plan they refer to.
- Check the issuing authority (HDMC for a building inside corporation limits), the date, the survey or property number and the number of floors and units. An OC for fewer floors than were built is a warning sign.
- Make sure it covers your block or tower, if the project has several.
- Compare the project's details on Karnataka RERA; see how to check a RERA project.
- For a resale flat, ask the seller for the OC as well as the e-khata, tax receipts and association no-dues letter.
If an under-construction project is running late on its OC, the builder's promised completion date in the RERA registration and your agreement still applies. Our guide to possession delay compensation explains what you can claim.
Sources
- Real Estate (Regulation and Development) Act, 2016 — Act text — Haryana Real Estate Regulatory Authority, accessed 26 November 2026
- The Karnataka Municipalities and Certain Other Law (Amendment) Bill, 2025 (LA Bill No. 53 of 2025) — Karnataka Legislative Assembly (via PRS Legislative Research), accessed 26 November 2026
- No loans, electricity, water and sewerage connections for buildings without completion/occupation certificate, orders SC — The Tribune, accessed 26 November 2026
- New home construction crisis in Karnataka — The Hans India, accessed 26 November 2026
- Bengaluru relief: no occupancy certificate needed for homes on plots up to 1,200 sq ft — Oneindia, accessed 26 November 2026
- Karnataka government grants OC exemption for 1200 sq. ft houses in Greater Bengaluru — The Hans India, accessed 26 November 2026
- Govt clears electricity connections for buildings without occupancy certificate — The Hans India, accessed 26 November 2026
- Exemption of occupancy certificate requirements for small residential buildings in Karnataka — Cyril Amarchand Mangaldas (Conventus Law), accessed 26 November 2026
- 15 day window for power connections without OC — Construction World, accessed 26 November 2026
Written by the Shriya Properties team in Hubballi and checked against the sources above on 26 November 2026. Rules, rates and prices change — confirm the current figures before you decide. Spotted something out of date? Tell us.
Questions buyers ask
What is the difference between a completion certificate and an occupancy certificate?
A completion certificate says the building was built according to the sanctioned plan. An occupancy certificate is the local authority’s permission to occupy it, and it is the document utilities and banks ask for.
Who issues the occupancy certificate in Hubli-Dharwad?
For buildings inside corporation limits, the Commissioner of the Hubballi-Dharwad Municipal Corporation, under section 310 of the Karnataka Municipal Corporations Act, 1976.
Can I get an electricity connection without an OC in Karnataka?
Not for a flat. Since the Supreme Court’s December 2024 ruling, permanent connections need a completion or occupancy certificate. Karnataka’s 2025-26 relaxations cover only small individual houses, not apartment buildings.
Will a bank give a home loan on a flat without an occupancy certificate?
For an under-construction flat, banks lend in stages against an approved project. For a completed building, the Supreme Court has directed banks to verify the completion or occupation certificate before lending against it.
Is it safe to buy a ready flat without an occupancy certificate?
It is risky. Without an OC you may not get permanent utilities, a smooth khata transfer or a loan, and you may find it hard to sell. Ask why the OC is pending and get legal advice before paying.