When a builder misses the possession date, refuses a refund or ignores defects, the Karnataka Real Estate Regulatory Authority (K-RERA) is the forum built for the dispute. Filing is online and the fee is small, so a buyer in Hubballi (Hubli), Dharwad, Bengaluru or abroad can start a case without travelling. Getting a good order is only half the job, though, and this guide is frank about the other half.
Section numbers refer to the Real Estate (Regulation and Development) Act, 2016 (Act text); rule numbers to the Karnataka RERA Rules, 2017 (rules text).
Who can complain, and about what
Section 31 lets any aggrieved person file a complaint against a promoter, an allottee or a real estate agent for any breach of the Act, rules or regulations. An association of allottees or a registered voluntary consumer association counts as a person, so a residents' association can complain about common areas.
The usual complaints are a delayed handover (possession delay), a refund that has not been paid (booking and refunds), defects not repaired (defect liability), more than 10% taken before a registered agreement, or a sale deed not registered. If a project was never registered, you can still report it: the authority's 2022 regulations say it may ask you for the promoter's details and start proceedings to register the project.
Authority or adjudicating officer: Form N or Form O
The Act has two decision-makers, and the Supreme Court drew the line between them in Newtech Promoters (November 2021): refund, interest on a refund, interest for delayed possession and penalties are for the Authority; compensation and interest on it, under sections 12, 14, 18 and 19, is for the adjudicating officer (judgment text).
| Authority | Adjudicating officer | |
|---|---|---|
| Decides | Refund, interest, delay interest, directions, penalties | Compensation for loss |
| Form | Form N (rule 29) | Form O (rule 30) |
| Fee | ₹1,000 | ₹1,000 |
| Time limit in the Act | None stated | Aim to decide within 60 days (section 71(2)) |
If you want both your money back with interest and compensation for losses such as rent paid while waiting, you will usually need both forms.
Filing online, step by step
The Karnataka RERA (General) Regulations, 2022 require Form N and Form O complaints to be lodged on the Karnataka RERA web portal with the fee (regulation 11). The steps, as a 2025 practitioner's guide describes them (TaxGuru, May 2025):
- Collect documents: agreement for sale, allotment letter, payment receipts and bank statements, letters and emails with the builder, home loan letters and any rent agreement if you claim losses.
- Register and log in at rera.karnataka.gov.in through the complaint registration page; the portal has its own user manual (archived complaint page).
- Choose the forum and provisions, and enter the project's RERA number and the promoter's details.
- State the facts in date order, briefly, and the relief precisely, for example "refund of ₹36,00,000 with interest at SBI MCLR plus 2% from each payment date".
- Upload the documents and pay the ₹1,000 fee. The 2017 rules mention a demand draft; check the payment mode the portal currently accepts.
- Submit and note the complaint number. An officer scrutinises each complaint and must tell you of any defects in it within seven days (regulation 11(3)).
The authority works in Kannada and English (regulation 4).
Hearings
Under rule 29, the authority sends the builder a notice with the allegations, the builder files a reply, and the matter is heard in a summary procedure. The authority can call for documents and evidence and can go ahead without a party who fails to appear. The 2025 guide says most matters take four or five hearings, and a complainant who repeatedly does not appear risks dismissal.
You do not have to attend every hearing yourself. Section 56 lets you appear in person or authorise an advocate, chartered accountant, company secretary or cost accountant, who files a memorandum of authorisation (regulation 13). That matters when the authority sits in Bengaluru and you live in Hubballi or overseas. The portal also shows complaint status and daily cause lists, and in 2024 it listed a mediation registration option and Lok Adalat orders, so settlement is possible. A certified copy of an order costs ₹100 per copy (regulation 19).
Appeals
Either side can appeal to the Karnataka Real Estate Appellate Tribunal within 60 days of receiving the order (section 44(2)); the tribunal can admit a late appeal for sufficient cause. The fee is ₹5,000, and the appeal is filed in Form R (rule 33). The tribunal is to try to decide within 60 days (section 44(5)).
A builder that appeals must first deposit with the tribunal at least 30% of any penalty, or the total amount payable to you including interest and compensation (section 43(5)). The Supreme Court upheld this pre-deposit in Newtech. A further appeal lies to the High Court within 60 days of the tribunal's decision, on limited grounds (section 58).
Worked example: what a case costs in fees
Say a Hubballi buyer seeks a refund of ₹36 lakh with about ₹7.2 lakh of interest, plus compensation for ₹2.4 lakh of rent paid while waiting.
| Item | Amount |
|---|---|
| Form N complaint (refund and interest) | ₹1,000 |
| Form O complaint (compensation) | ₹1,000 |
| Two certified copies of orders | ₹200 |
| Official fees | ₹2,200 |
| If the builder appeals, it must first deposit | The full amount ordered for you |
| If you appeal | ₹5,000 |
Advocate's fees are extra and vary.
Turning an order into money
If the builder does not pay, section 40(1) makes the amount recoverable as arrears of land revenue. Karnataka RERA issues a recovery certificate and the revenue department, through the Deputy Commissioner and tahsildar of the district, recovers it; for a Hubballi-Dharwad project that is the Dharwad district administration. Ignoring the authority's orders can also cost a builder a penalty of up to 5% of the project cost (section 63).
Recovery is where Karnataka struggles. Deccan Herald reported in February 2026 that of 2,338 cases with recovery orders since July 2017, only 291 buyers, about 12.45%, had actually been paid, with files often stuck in the revenue department (Deccan Herald, February 2026). In April 2026 it reported about ₹110 crore recovered of about ₹1,081 crore ordered, and that the authority had sought a dedicated recovery cell (Deccan Herald, April 2026). Follow up with the district office in person or through your representative.
RERA or the consumer commission?
You can also go to a consumer commission, but choose once. The Supreme Court held in 2020 that RERA does not bar consumer complaints, yet on 5 March 2026 it held that buyers who pursue RERA cannot later approach a consumer commission for the same cause. Lawyers quoted by Business Standard in September 2026 suggest RERA for delays, refunds and statutory interest, and consumer commissions for deficient service and wider damages; consumer complaints generally have a two-year limitation period, while section 31 sets none. Once you have an order, enforce it rather than starting again elsewhere.
The best complaint is the one you never need: checking a builder's RERA record before booking, as in our guide on how to check a RERA project, shows past complaints and orders against it. Where that check fits in the purchase is set out in our step-by-step buying guide.
Sources
- Real Estate (Regulation and Development) Act, 2016 — Act text — Haryana Real Estate Regulatory Authority, accessed 26 November 2026
- Karnataka Real Estate (Regulation and Development) Rules, 2017 (rules 29, 30, 33) — Legitquest, accessed 26 November 2026
- Karnataka Real Estate Regulatory Authority (General) Regulations, 2022 — Legitquest, accessed 26 November 2026
- Complaint login page, Karnataka RERA portal (archived May 2024) — Karnataka Real Estate Regulatory Authority, via Internet Archive, accessed 26 November 2026
- Dispute resolution for homebuyers: RERA complaint mechanism explained, Karnataka (16 May 2025) — TaxGuru, accessed 26 November 2026
- Newtech Promoters and Developers Pvt. Ltd. v. State of UP, judgment of 11 November 2021 (LL 2021 SC 641) — Supreme Court of India (copy hosted by LiveLaw), accessed 26 November 2026
- K-RERA orders: why homebuyers in Karnataka are still without relief in 2026 (14 February 2026) — Deccan Herald, accessed 26 November 2026
- Rs 1,000-crore RERA recovery for Bengaluru homebuyers delayed (26 April 2026) — Deccan Herald, accessed 26 November 2026
- Rera or consumer commission: why forum should be chosen with care (15 September 2026) — Business Standard, accessed 26 November 2026
Written by the Shriya Properties team in Hubballi and checked against the sources above on 26 November 2026. Rules, rates and prices change — confirm the current figures before you decide. Spotted something out of date? Tell us.
Questions buyers ask
What is the fee for a RERA complaint in Karnataka?
₹1,000 for a complaint to the Authority in Form N and ₹1,000 for a compensation complaint to the adjudicating officer in Form O, under rules 29 and 30 of the Karnataka RERA Rules.
Can I file a Karnataka RERA complaint online?
Yes. The 2022 regulations require Form N and Form O complaints to be lodged on the Karnataka RERA portal with the fee. You register on the complaint page, fill the details, upload documents and pay.
What is the difference between Form N and Form O?
Form N goes to the Authority for refunds, interest, delay interest and directions. Form O goes to the adjudicating officer for compensation under sections 12, 14, 18 and 19.
How do I appeal against a Karnataka RERA order?
Appeal to the Karnataka Real Estate Appellate Tribunal within 60 days of receiving the order, in Form R with a ₹5,000 fee. A builder must first deposit the amount payable to you, or at least 30% of a penalty.
What happens if the builder does not obey a RERA order?
The amount can be recovered as arrears of land revenue under section 40 through the district revenue authorities, and the builder can be penalised up to 5% of the project cost. Recovery in Karnataka is often slow.
Can I go to both RERA and the consumer court?
Not for the same cause. In March 2026 the Supreme Court held that buyers who pursue RERA cannot later approach a consumer commission for the same dispute.