Hubballi-Dharwad Infrastructure and Growth Projects: 2026 Status

Which projects are open, which are being built and which are still on paper, checked against official data and news reports in November 2026.

By Shriya PropertiesUpdated 26 November 20267 min read

Every property brochure in Hubballi (Hubli) lists the same projects: a new airport terminal, new rail lines, an industrial cluster, IIT Dharwad. Some are finished, some are being built and some have been "coming soon" for decades. This page sorts them by status as of November 2026, with a source for each, so you can tell what is already part of the city and what is still a promise.

Status at a glance

Project What it is Status, November 2026
Hubballi airport traffic Flights to Bengaluru, Mumbai, Delhi, Hyderabad, Chennai, Pune and Navi Mumbai Operating; 3.76 lakh passengers in 2025-26, up 8.6%
New airport terminal 20,000 sq.m, about 2,400 passengers at a time Under construction since March 2024; no opening date found
South Western Railway HQ Zone headquarters at Hubballi Operating since 2003
Longest platform 1,507 m at Hubballi Junction Opened March 2023
Bengaluru–Belagavi Vande Bharat Stops at Hubballi and Dharwad Running since August 2025
Dharwad–Kittur–Belagavi line 73 km new line Land mostly acquired; groundwork expected by December 2026
Hubballi–Ankola line 163 km double line to the coast Revised plan approved by Railway Board; wildlife clearances pending
BRTS 22.25 km bus corridor between the cities Operating since 2018
Light rail on the BRTS corridor Proposed in 2023 No approval found
Bypass six-laning About 30 km of NH-48 bypass Tendered in 2022; current progress not confirmed
Smart City works Lakes, green corridor, parks 59 of 63 projects done by October 2023
Consumer-goods cluster Aequs, 400 acres Launched October 2024
IIT Dharwad Permanent campus Opened March 2023

Air

Traffic. Hubballi airport handled 3,76,286 passengers in April 2025 to March 2026, up 8.6%. April to September 2026 was another 9.9% higher than a year earlier (Airports Authority of India). That makes it busier than Belagavi, which fell 11.4%. It is still short of the 4.75 lakh it handled in 2019-20.

Routes. In late 2026 IndiGo flies to Bengaluru, Chennai, Delhi, Hyderabad, Mumbai, Navi Mumbai and Pune, and Fly91 to Bengaluru and Hyderabad.

New terminal. The current terminal opened in 2017. It covers 3,600 sq.m and handles about 600 passengers at a time. The new one will cover about 20,000 sq.m and handle about 2,400. It is part of a roughly ₹270 crore upgrade that also adds apron space for ten Code C aircraft instead of three, plus aerobridges. The foundation stone was laid in March 2024, and the terminal was expected to open in 2026. We found no opening announcement as of November 2026, so treat a 2027 opening as realistic rather than certain.

What it means. Better flights help most in the localities closest to the airport, on Gokul Road and around it. They also help anyone who works in another city and flies home.

Rail

Railway headquarters. Hubballi has been the headquarters of the South Western Railway zone since 2003. Its Hubballi division is the zone's largest, with about 1,435 route km as of April 2026. A large central-government employer is one of the steadiest sources of housing demand a city can have.

Station and Vande Bharat.

  • The platform. Hubballi Junction's 1,507-metre platform was the world's longest when it opened in March 2023.
  • Vande Bharat. Since August 2025 the Bengaluru–Belagavi Vande Bharat Express has stopped at Hubballi and Dharwad. It covers the 611 km Bengaluru–Belagavi run in about 8.5 hours.

Dharwad–Kittur–Belagavi line. This 73 km new line would cut the rail distance between Dharwad and Belagavi. Reports in early 2026 conflicted about land:

  • On 6 February 2026 the Railway Minister told the Rajya Sabha no land had yet been acquired.
  • By April, local reports said about 1,200 of roughly 1,436 acres had been acquired. ₹300 crore of compensation had been sanctioned and ₹60 crore paid.
  • The project is shared 50:50 by the Centre and the state, and groundwork was expected to begin by December 2026.

Hubballi–Ankola line. First announced in the late 1990s, this line would link Hubballi to the coast and the ports beyond. Work on an early stretch towards Kalaghatgi stopped over environmental objections and a court case.

  • Revised plan. The plan is now a 163 km electrified double line with about 57 tunnels, estimated at ₹16,453 crore. In July 2026 the Railway Board declared it a special railway project by gazette notification, and South Western Railway began the land-acquisition process.
  • Still pending. Wildlife and other clearances were still pending in August 2026, and no construction date has been announced.

What it means. Treat this line as a long-term possibility, not a reason to pay more for a flat today.

Roads and city transport

BRTS. The Hubballi–Dharwad BRTS runs 22.25 km between the two central bus terminals and began operating in October 2018.

  • Cost. It cost about ₹970 crore, with World Bank support.
  • Ridership. The World Bank reported about 90,000 riders a day within a year of launch.
  • Speed. Limited-stop buses take about 35 minutes end to end.

Light rail idea. In July 2023 the district minister said the government was planning a light rail line using space in the BRTS corridor, possibly as a public-private partnership. We found no approval or detailed project report since. Do not count on it.

Bypass six-laning. In January 2022 NHAI invited bids to widen the two-lane Hubballi–Dharwad bypass on NH-48 to six lanes. The tender estimated about ₹799 crore and covered:

  • about 29.5 km of service roads on both sides
  • a grade separator at Gabbur junction
  • a single toll plaza in place of several

The tender allowed two and a half years for construction. We could not confirm its progress as of November 2026, so check before relying on it.

Smart City works

Hubballi-Dharwad was one of the cities picked under the national Smart Cities Mission. By October 2023 its Smart City company had finished 59 of 63 projects worth ₹810 crore (PTI). Two stand out:

  • Tolankere lake. The 39-acre lake was restored at a cost of about ₹25 crore, with walkways and play areas.
  • Green Mobility Corridor. A stormwater drain was turned into a fenced, lit walking and cycling route. The planned route is 9.4 km and starts at Unkal Lake; 4.5 km was complete at the time. Officials said the drain walls ended flooding along its banks in the 2022 monsoon.

Works like these matter more to day-to-day life, and to prices in the streets around them, than most announcements.

Industry and jobs

Aequs consumer-goods cluster. Aequs Infra began developing a 400-acre consumer durables cluster in Hubballi in January 2022, planning about 4.5 million sq.ft of factory space. In October 2024 Aequs launched an FMCG manufacturing ecosystem there, unveiled by the state's industries minister. Units setting up get a 20% capital subsidy, capped at ₹25 crore, and a 3% turnover-linked incentive for five years.

Beyond Bengaluru. Karnataka's Beyond Bengaluru programme names Hubballi-Dharwad-Belagavi as one of six clusters for IT, electronics and manufacturing. The state's IT Policy 2025–30, with an outlay of ₹967 crore, supports companies that relocate staff and rent offices outside Bengaluru.

Existing IT space. The twin cities already have a Software Technology Park on the Dharwad road and the Aryabhata Tech Park in Navanagar.

What it means. Factory jobs raise demand first for rentals and plots on the industrial side of town. IT and engineering jobs are the ones that lift demand for mid-size and larger flats.

Education and health

Education. Dharwad has long been an education town, and the twin cities now have two national institutes as well as older universities:

Institution Where Key facts
IIT Dharwad Chikkamalligawad, Dharwad Founded 2016; 470-acre permanent campus opened 12 March 2023; 77th among engineering institutes in NIRF 2025
IIIT Dharwad Tadasinakoppa, Dharwad Founded 2015; 60-acre campus in use since 2021
Karnatak University Pavate Nagar, Dharwad Founded 1950; 888 acres; NAAC 'A' (2022); 250+ affiliated colleges
KLE Technological University Hubballi Roots in 1947; university since 2012; 64 acres; about 3,500 undergraduates

Health.

  • KIMS. Hubballi's government medical college and hospital, KIMS, was founded in 1957 on a 100-acre campus near Vidyanagar. It provides tertiary care to patients from across the region.
  • Private hospitals. SDM's hospital on the Dharwad side and several private hospitals add specialist care.

What it means. Colleges and hospitals do not relocate, and they bring steady demand for rentals from students, faculty and medical staff. Homes within a short commute of them tend to rent and resell more easily.

What to price in

When a seller lists "upcoming" projects, sort them into three groups:

  1. Built and working. The airport and its routes, the railway headquarters, the BRTS, Vande Bharat, IIT and IIIT Dharwad, KIMS, and the Smart City lakes and corridor. These are already in today's prices.
  2. Under construction with money committed. The new airport terminal and the Dharwad–Kittur–Belagavi line. Fair to count on, with some delay.
  3. Approved or proposed, with hurdles. The Hubballi–Ankola line and light rail. Do not pay extra for these.

For how these feed into prices by locality, see our 2026 market report. For how Hubballi compares with other Karnataka cities, see where to invest in Karnataka.

Sources

  1. AAI traffic news, Annexure III-C, March 2026 — Airports Authority of India, accessed 26 November 2026
  2. AAI traffic news, Annexure III-C, September 2026 — Airports Authority of India, accessed 26 November 2026
  3. Hubli Airport — Wikipedia, accessed 26 November 2026
  4. Hubballi Airport upgrade to host bigger aircraft soon — Construction World, accessed 26 November 2026
  5. Karnataka seeks new airports as Hubballi traffic climbs — Construction World, accessed 26 November 2026
  6. South Western Railway zone — Wikipedia, accessed 26 November 2026
  7. Hubballi Junction railway station — Wikipedia, accessed 26 November 2026
  8. PM Modi flags off three Vande Bharat Express trains in Bengaluru — ThePrint, accessed 26 November 2026
  9. Belagavi–Dharwad rail line back on track — All About Belgaum, accessed 26 November 2026
  10. Rail minister on Dharwad–Belagavi land acquisition (Rajya Sabha) — All About Belgaum, accessed 26 November 2026
  11. Hubballi-Ankola new railway line project gets Rail Board nod (Kannada) — Oneindia Kannada, accessed 26 November 2026
  12. Three-decade dream realised: Centre approves Hubballi-Ankola railway line project — Daijiworld, accessed 26 November 2026
  13. Hubli-Dharwad Bus Rapid Transit System — Wikipedia, accessed 26 November 2026
  14. India: New Bus Rapid Transit System makes travel faster, safer and more convenient in Hubballi-Dharwad — World Bank, accessed 26 November 2026
  15. Next-generation mobility: Hubballi-Dharwad to embrace light rail transit — Swarajya, accessed 26 November 2026
  16. RFP tender invited for upgradation of Hubballi-Dharwad bypass with six lane — Mysuru Infra Hub, accessed 26 November 2026
  17. Redevelopment projects worth Rs 810 crore give Hubballi a face lift — ThePrint (PTI), accessed 26 November 2026
  18. After toy cluster, Aequs begins work on consumer goods cluster in Hubballi — Swarajya, accessed 26 November 2026
  19. Aequs Infra launches FMCG manufacturing ecosystem in Karnataka — ThePrint (PTI), accessed 26 November 2026
  20. Beyond Bengaluru: building Karnataka’s next network of growth cities — Elets eGov, accessed 26 November 2026
  21. Hubli (city) — economy — Wikipedia, accessed 26 November 2026
  22. Indian Institute of Technology Dharwad — Wikipedia, accessed 26 November 2026
  23. Indian Institute of Information Technology, Dharwad — Wikipedia, accessed 26 November 2026
  24. Karnatak University — Wikipedia, accessed 26 November 2026
  25. KLE Technological University — Wikipedia, accessed 26 November 2026
  26. Karnataka Institute of Medical Sciences — Wikipedia, accessed 26 November 2026

Written by the Shriya Properties team in Hubballi and checked against the sources above on 26 November 2026. Rules, rates and prices change — confirm the current figures before you decide. Spotted something out of date? Tell us.

Questions buyers ask

When will the new Hubballi airport terminal open?

The 20,000 sq.m terminal has been under construction since March 2024 and was expected to open in 2026. We found no opening announcement as of November 2026, so a 2027 opening is more realistic.

What is the status of the Hubballi–Ankola railway line?

The Railway Board approved a revised plan for a 163 km double line estimated at ₹16,453 crore and notified it as a special railway project in July 2026, but wildlife and other clearances were still pending and no construction start has been announced.

Is the Dharwad–Kittur–Belagavi railway line approved?

Yes. It is a 73 km line shared 50:50 by the Centre and Karnataka. By April 2026 about 1,200 of roughly 1,436 acres had been acquired, with groundwork expected by December 2026.

How long does the BRTS take from Hubballi to Dharwad?

About 35 minutes on limited-stop services and about 55 minutes on all-stop services over the 22.25 km corridor.

Is Hubballi the headquarters of South Western Railway?

Yes. Hubballi has been the zone’s headquarters since it was formed in 2003, and the Hubballi division is the zone’s largest by route length.